MARIGOLD CLOSE PHASE 1 & 2 - COMPLETED PROJECT

02/FEBRUARY/2016

 

Location: Gurnos, Merthyr Tydfil

Client: Merthyr Value Homes

Project term: 12 months

Project period: Feb 2015 - Feb 2016

Value: £2.1 million

Structure: Lightweight steel frame

Scope of work: Construction of twenty one units consisting of three bungalows, two houses and sixteen flats; using a monocouche render finish to compliment the existing properties within the local community. The development also includes an extensive landscaping scheme within and around the site boundaries to renovate and transform the existing surroundings 

 

         

 

Phase 3

Client: Merthyr Valley Homes

Project term: 9 months

Completion date: December 2015

Value: £700,000

Structure: Lightweight steel frame

Scope of work: Demolition of existing structure containing siz maisonette flats and a nursery centre. Construction of six units consisting of six houses; using a monocouche render finish to compliment the existing properties within the local community. 

 

   

    

About Us

Kathrens Holdings was formed in 2007 as a Holding company for WK Plasterers Ltd  and it's associate Company,Carbis Properties Ltd. WK Plasterers Ltd  was set up in 1971 providing operatives to the Volume New Build Sector.

The Group has then developed further by adding the subsiduaries, KEEBS & Carbis Partnership Homes.

Through recent years the company has pushed into new areas of trade with a key emphasis on the Enhancement And Upgrading of Traditional Build Systems by using novel and innovative solutions.

All Operations are orchestrated from Head Office based in Pontypridd South Wales with a annual turnover in excess of 14 million a year and over 6 million of assets Kathrens Holdings has forged a strong position within its core activity within South Wales and West of England. 

Read More
Get in Touch

Please enter your details below and we will contact you: